井架如何穿大绳


井架如何穿大绳 崔智德 Reeving drilling line on empty sheaves with a standing derrick 塔式井架穿大绳程序 1. Disengage the crown-o-matic and, place the traveling block on the rotary table and remove the sheaves g

uard. 卸掉防碰天车,把游车放到转盘上,再卸掉滑轮护罩。 2. Anchor the proper size snatch block at or near the dead line anchor and secure. 在死绳固定器上,或旁边装一个开口滑轮,绑好。 3. Insert the drilling line from the spool through the snatch block up to the rig floor and secure. 把大绳从储备筒上拉出来,穿过开口滑轮,引上钻台,绑住。 4. Thoroughly clean the section of the new drilling line to be spliced with the snake, and remove any grease or oil (the snake line depends on friction to function). 彻底清洗新大绳穿入蛇皮接绳器的部位,把油污都弄掉。(蛇皮接绳器主要靠摩擦锁紧) 5. Attach a 1-1/2 inch snake to the drilling line. Ensure that the snake is correctly in place over its full length. 把大绳穿到一寸半的蛇皮接绳器内,保证适当就位,长度足够。 6. For added holding and pulling strength, drive four nails through the snake and the drilling line, and wrap the snake with soft wire and tape the entire length. 为了增加抗拉强度,在穿接绳器的部位,再钉四个钉子,然后用铁丝和胶带包起来。 7. Raise one end of 600 meter long and 1 inch in diameter manila rope to the crown block with air tugger.

用气动绞车,把一盘一寸的,长六百米的棕绳的一头弄到天车上去。 8. Reeve the 1 inch manila rope through the first crown sheave. 把棕绳穿过天车上的第一个滑轮。 9. Lower the 1 inch manila rope to the rig floor and reeve into the first sheave of the traveling block. 把棕绳下放到钻台上,再穿过游车的第一个滑轮。 10. Repeat steps from G to I until all the sheaves are reeved in. 重复从 G 到 I 的步骤,把所有的滑轮都穿完。 11. Remove the front guard cover of the drawworks. 卸掉绞车前边的护罩。 12. Lower the 1 inch manila rope down from the fast line sheave and wind on the drawworks drum. 从快绳轮上把棕绳放下来,再缠到绞车辊筒上。 13. Manually reeve 6 wraps of the 1 inch manila rope on to the drawworks drum. 把棕绳在绞车辊筒上缠六圈。 14. Attach the other end of the 1 inch manila rope to the snake on the drilling line. 把棕绳的另一头穿到蛇皮接绳器上,和大绳接到一起。 15. The derrick man, positioned at the crown block, is to advise the driller when the snake is coming through the crown sheave. The driller and the derrick man must remain in constant radio contact. 井架工看守在天车上,当蛇皮接绳器到达天车时,通知司钻。司钻和井架工必须用对讲机一直 保持联系。 16. Two floormen, located at the new drilling line spool, are to reeve off the drilling line without delay.

两个钻工看守在新大绳储备筒旁边,及时地放出大绳。 17. One floor man should stand close to the spool to inform the driller with a two-way radio when there is no loose drilling line coming off the spool. 让一个钻工站在大绳储备筒旁边,用对讲机把大绳的松紧情况通知司钻。 18. The driller is to proceed cautiously and not pull excessive tension that could separate the snake. 司钻小心缓慢地操作,以防把蛇皮接绳器拉断。 19. When all personnel are ready, the driller engages the drawworks in forward drive and starts reeving in the new drilling line. At the same time, two floor men guide the 1 inch manila rope off the drawworks drum onto the rig floor or down the v-door. 人员都就位后,司钻启动绞车正转,开始缠新大绳。同时,让两个钻工把从辊筒上退下来的棕 绳盘到钻台上,或盘到大门下边去。 20. The driller should spool slowly and with extreme caution, not to over-tension the snake until the new drilling line is on the drawworks drum. 司钻特别小心地往辊筒上缠绳,注意拉力不要超过接绳器的强度,直到把新大绳都缠在辊筒上。 21. When the drilling line reaches the drawworks drum pull through 9 wraps of the drilling line to enable the drilling line to be threaded onto the drawworks drum. 当大绳到达绞车辊筒时,拉出能够在绞车辊筒上缠九圈的大绳。 22. The driller must ensure the fast line is securely tied off so that it can not unreeve by itself. 司钻一定要把快绳绑好,以防快绳自己退下来。 23. With the fast line tied off, remove the snake from the drilling line, and remove the 1 inch manila rope from the drawworks drum. 把快绳绑好之后,从大绳和棕绳之间把蛇皮接绳器卸下来。把棕绳从绞车辊筒上退下 来。

24. Install a new drawworks anchor clamp (bulldog clamp). Orient the clamp and ensure that it will fit through the slot on the side of the drawworks drum. Note: some drawworks are equipped with a fixed clamp on the side of the drum. 装一个新的活绳头卡子。把卡子摆正。保证该卡子坐在绞车辊筒边上的槽内。注意:在有些绞 车辊筒的一边配了固定的活绳头卡子。 25. Set the anchor clamp onto the drum by manually pulling the new drilling line back through the drum, with a floor man guiding it into the drum. 由一个钻工扶着,从辊筒上往回拉新大绳,使活绳头卡子在辊筒上就位。 26. Warning: ensure that no person is inside the loop of the drilling line during the next step. 注意:在进行下一步作业时,人不能站在大绳盘的环内。 27.The driller engages the drawworks in forward drive and reeves the new drilling line back onto the drawworks drum. Reeve in as a minimum of 9 wraps with the elevators on the rotary table. 司钻启动绞车正转,把新大绳排到辊筒上。当吊卡处在转盘面时,辊筒上至少缠九圈。 28.The driller must ensure that the drilling line is reeved in under tension and that the drilling line is properly seated in the drum grooves. There is no tolerance for any slack in the drilling reeved on the drum. 司钻必须在大绳处于拉伸状态下缠绳,使大绳与排绳槽吻合。缠到辊筒上的大绳不能有任何间 隙和松动。 29. Secure the drilling line to the dead line anchor (2-3/4) wraps, and torque. 把大绳在死绳固定器上缠 2-3/4 圈,排紧。 30. With the new drilling line properly reeved on to the drawworks drum, pick up the weight of the traveling block, test the drawworks brake, and verify that the drilling line is tight on the drum. 当新大绳在绞车辊筒上都排好之后,上提游车,试绞车的刹车,检查辊筒上的大绳是否排紧。 31. Install the covers on the drawworks .

装上绞车护罩。 32. Ensure the crown-o-matic and test. 装上防碰天车,并做试验。

Reeving in the drilling line to raise the mast A 型井架穿大绳程序 1. Secure the traveling block to the catwalk, with the sheaves aligned with the crown and the hook pointed upward, with the raising line attached. 把游车滑轮对准天车,把大钩挂到起井架大绳上,把游车绑在锚道上。 2. Attach a proper size snatch block at or near the dead line anchor and secure. 把一个适当尺寸的开口滑轮绑在死绳固定器上(或旁边)。 3. Feed the drilling line through the snatch block near the dead line anchor. 把大绳穿过死绳固定器旁边的开口滑轮。 4. Thoroughly clean the section of the drilling line to be covered with the snake and remove any grease or oil (the snake line function by friction). 彻底清洗大绳头,把蛇皮接绳器覆盖部位的油污都清理掉(蛇皮接绳器靠的是摩擦锁紧)。 5. Attach the 1-1/2 inch snake to the drilling line. Ensure that the snake is correctly in place over its full length. 把大绳穿到一寸半的蛇皮接绳器内,保证把足够长的大绳穿入适当的部位。

6. For added holding and pulling strength, drive four nails through the snake and the drilling line, wrap the snake with soft wire and tape the entire length. 为了增加抗拉强度,在穿蛇皮接绳器的部位再钉四个钉子,然后用铁丝和胶带包起来。 7. Remove the sheave guards on the traveling block. 卸掉游车轮上的护罩。 8. Pull the 1 inch manila rope inside the derrick and feed and reeve through the first crown sheave. 把一寸的棕绳穿过天车上的第一个滑轮,在井架内拉该棕绳。 9. From the crown sheave, manually pull and reeve the 1 inch manila rope through the first sheave of the traveling block. 用人力把棕绳从天车轮上拉过来,再穿过第一个游车轮。 10. Repeat steps from H to I until the sheaves are reeved in. 重复从 H 到 I 的步骤,把滑轮都穿完。 11. Next, reeve the 1 inch manila rope through the fast line sheave and pull back to the drawworks drum. 下一步,把棕绳穿过天车上的快绳轮,再拉回到绞车辊筒。 12. Remove the front cover of the drawworks. 卸掉绞车前边的护罩。 13. Manually reeve 6 wraps of the 1 inch manila rope onto the drawworks drum. 把一寸的棕绳在绞车辊筒上缠六圈。 14. Attach the other end of the 1 inch manila rope to the snake on the drilling line. 把棕绳的另一头,穿入蛇皮接绳器与大绳接起来。

15. The crew members are positioned as follows: 井队人员分工如下: a. The derrick man is at the crown block. 井架工看守天车; b. Two floor men are at the drilling line spool. 两个钻工看守大绳储备筒; c. Two floor men are at the drawworks drum. 两个钻工看守绞车辊筒; d. Direct two-way radio communication is essential from each other. 相互间用对讲机联系是很必要的。 16. The driller engages the drawworks in forward drive and pulls the 1 inch manila rope onto the drawworks drum. 司钻启动绞车正转,用绞车辊筒拉棕绳。 17. At the same time, two floor men at the drawworks guide the 1 inch manila rope coming from the drawworks back onto the rig floor or down the v-door. 同时,让两个钻工把从绞车辊筒上退下来的棕绳盘到钻台上或盘到大门下边。 18. The driller continues pulling in the drilling line until the crown and traveling blocks have been completely reeved, plus 9 wraps of excess drilling line to be wrapped onto the drawworks. 司钻继续拉大绳,直到把天车和游车上的滑轮都穿完,再加上能在绞车辊筒上缠九圈的余量。 19. The driller must ensure the fast line is securely tied off so that it can not be unreeved by itself. 司钻必须把快绳绑好,以防大绳自己倒退。

20. With the fast line tied off, remove the snake from the drilling line, and remove the 1 inch rope from the drawworks drum. 把快绳绑好之后,从大绳上把蛇皮接绳器卸下来。再把棕绳从绞车辊筒上弄下来。 21. A floor man cleans the end of the fast line using a wire brush and detergent fluid. 让一个钻工用钢丝刷子和洗涤剂清洗快绳头。 22. The driller checks the end of the new drilling line for damage, and cut off any defective section by using of a hydraulic line cutter. 司钻检查新大绳的快绳头,如有任何损伤或缺陷,就用液压切绳器把它切掉。 23. Feed the new drilling line (fast line) through the side of the drawworks drum. 把快绳头穿过绞车辊筒的一边。 24. Install a new drawworks anchor clamp (bulldog clamp). Orient the clamp and ensure that it will fit through the slot on the side of the drawworks drum. Note:Some drawworks are equipped with a fixed clamp on the side of the drum. 装一个新活绳头卡子,把卡子摆正,保证该卡子坐在绞车辊筒边上的槽内。注意: 有些绞车辊筒的一边,配备了固定的活绳头卡子。 25. Set the anchor clamp onto the drum by manually pulling the new drilling line back through the drum, with a floor man guiding it into the drum. 由一个钻工扶着,从辊筒上往回拉新大绳,使活绳头卡子在辊筒上就位。 26. Release the new drilling line from the side of the drawworks. Warning : ensure that no person is inside the loop of the drilling line during the next step. 从绞车辊筒的一头放下新大绳。注意:在进行下一步作业时,人不能站在大绳盘的环内。 27. The driller engages the drawworks in forward drive and reeves the new drilling line back onto the drawworks drum. Reeve in as a minimum of 9 wraps with the elevators on the rotary table.

司钻启动绞车正转,把新大绳再排到绞车的辊筒上。当吊卡处在转盘面时,辊筒上至少缠九圈。 28. The driller must ensure that the drilling line is reeved in under tension and that the drilling line is properly seated in the drum grooves. There is no tolerance for any slack in the drilling line reeved on the drum. 司钻必须在大绳处于拉伸状态下缠绳,使大绳与辊筒排绳槽吻合。缠到辊筒上的大绳不能有任 何间隙和松动。 29. Secure the drilling line to the dead line anchor (2-3/4 wraps) and torque. 把大绳在死绳固定器上缠 2-3/4 圈,排紧。 30. Install the traveling block sheave guards. 把游动滑车护罩装上。 31. Install the front drawworks guard cover after the mast is raised. 井架起来之后,把绞车前边的护罩装上。


相关文章:
井架如何穿大绳
井架如何穿大绳_能源/化工_工程科技_专业资料。井架如何穿大绳 崔智德 Reeving drilling line on empty sheaves with a standing derrick 塔式井架穿大绳程序 1....
起升井架大绳
起升井架大绳 2008-06-24 10:23:33 (已经被浏览 365 次) 缑庆林 油田...井架如何穿大绳 9页 免费 关于立井井架主提升绳更... 3页 免费 70D井架起升...
平衡穿绳法在竖立大型钢井架中的应用
平衡穿绳法在竖立大型钢井架中的应用 【摘要】 阐述了在煤矿大型钢井架竖立中应用平衡穿绳法的重要意义,介 绍了某煤矿大型钢井架竖立工程概况及施工作业过程, 对...
起井架大绳检查记录
井架如何穿大绳 9页 免费 井架绷绳地锚起下装置的... 暂无评价 2页 免费 ...钻井公司各钻井队起放井架大绳记录序号 1 钻井队 井号 50549 队玉东 2-6 ...
平衡穿绳法在竖立大型钢井架中的应用
平​衡​穿​​法​在​竖​立​大​型​钢​井​架​中​的​应​用 暂无评价|0人阅读|0次下载平衡穿绳法在竖立大型钢井架中...
钻井大绳滑绳、割绳作业和大绳的正确使用
滑绳与割绳长度又该如何确定呢? 三. 钻井大绳割...割绳前大绳累积功——钢丝绳直径(mm)的函数 井架...原因:穿绳或滑绳方法不正确、提升装置有损伤。 9....
起放井架操作规程
7、穿好井架和支架处的联接销,使井架固定。并将起升大绳从平衡三角架取下, 保养固定。 8、放井架前按安装钻台相反的顺序将各部件拆除。将起架钢丝绳与游车...
井架安装顺序
三、四节 井架——二层台——上横梁——天车——井架各附带件(逃走通道绳、架工助力器绳、绷绳)——挂 起升井架大绳——穿大绳(顺穿)——绞大绳上绞车...
起井架注意事项
. 起井架注意事项 为规范井队正规化管理,保证起...大绳穿法是否正确,钻井用索具、钻井大绳的死绳、...如何选择安全的航班 正确使用机上氧气面罩©...
放井架作业
5 人员在放井架危险区域内可能造成伤害。 6 起井架大绳固定松脱、超标使用未及时更换导致放井架过程中起升大绳 断裂,造成摔井架、伤人。 防范措施 1 钻井队组织...