Floating head heat exchanger manufacturing operating instructions

1. 材 料 确 认 : 在 材 料 管 理 员 的 指 导 下 , 对 材 料 的 标 记 确 认 。

Confirm material: under

the guidance of

materials

administrator ,recognized the mark of the material。
2.根据工艺排版图将板料平铺于切割架上,号料划出切割线、刨边线、检查线。 According to process diagram ,layouting the material

board on the shelves, cutting and draw the cutting line, plane edge, checking line. ,完成后对坡口进行超声检测。Groove processing (see groove process card), Ultrasonic testing 3.坡口加工(见坡口工艺卡) after the completion of the groove。 将坡口加工完好的板料置于卷板机上、 下辊轮间, 板料周长方向与辊轮垂直, 纵向与辊轮平行。 筒 节 4.卷板: Coil: place the groove processing Tube intact sheet on the rolling machine, between the upper and lower roller, the sheet perimeter direction is vertical to the section roller, and the longitudinal is parallel to the rooler. 将纵缝口两端对齐, 控制错边量, 错边不大于 1/4δ且不大于 2mm, 并点上引弧板。 Combine the longitudinal seam: Align both 5.纵缝组对: ends of the longitudinal seam, control the amount of the Staggered side,the staggered side is not greater than 1/4δ and not greater than 2mm, and point the arc plate. 6.纵缝焊接,见焊接工艺卡。 Longitudinal seam welding, see the welding process card。 7.校园: 不园度控制在 0.5%DN,且不大于 5mm,DN≥1200,不大于 7mm; 棱角度, 控制在δS/10+2, 且不大于 5mm。 Regulate to make sure it circle: Park, control the degree of of-roundness at 0.5% the DN, and not more than 5mm, the DN ≥ 1200,not more than 7mm; the angularity, should be controlled at δS/10 +2, and not more than 5mm。
1.将各筒节按排版图要求组对,各缝分布于 0~180°,互错 180°,环缝组对间隙 0~2mm。 According to the requirements of each tube

section layout diagram,combine them, each seam is distributed in the 0 to 180 ° , Stagger 180 ° ,the circumferential seam combination gap is 0 ~ 2mm. 筒 体 2.组对完毕后,从 0°、90°、180°、270°四个方位检测,直线度 10%,且不大于 4.5mm。.Detect after the combination of the 0 ° 90 ° , , Tube 180 ° 270 ° four orientation, 10% straightness, and no larger than 4.5mm. , Body 3.环缝棱角度控制在δS/10+2,且不大于 5mm 错边量。 Control the ring slit angular degree at δS/10+2, no larger than 5mm Staggerion of the volume. 4.环缝组对时不可强行组装,可用加减丝扣调节间隙,间隙在 0~1.5mm 最佳。 When combine the Circumferential seam ,we must not assemble forcibly,use the available subtraction threaded to adjust the gap, the gap is at best in the 0 ~ 1.5mm.
编制/日期: 校对/日期: 审核/日期: -1-

浮头式换热器制造工艺作业指导书

Floating head heat exchanger manufacturing operating instructions

5.确定错边值后,依次从最佳点入手,顺势而成,环缝错边量不得大于 1/4δ板厚且不大于 2mm。 Determining the value of the Stagger,

start from the best point by turn, homeopathy to be it, the circumferential seam should not be than 1/4δ plate thickness and not more than 2mm. 6.对组装后的筒体进行直线度检测,四点方位,其最大差值不得大于 4.5mm。Test the straightness after assembling the cylinder, four piont position, the maximum difference is not greater than 4.5mm。

贴有合格标签的, 对应的流水号和产品编号的。 The flange must be tested, labelled with a qualified label, the 1.法兰必须是经过检验,

corresponding serial number and product number.
2.用直尺划出法兰螺栓孔跨中线,与筒体纵缝线平行组装。 Draw the flange bolt holes across the center line with a ruler, assemble 筒体 与 法兰 组对

and make sure it parallel to the cylinder longitudinal suture.
右两侧),均分法兰孔,四等分。 Turn the one end installed flange 3.将装一端法兰的筒体,纵缝方向转至 90°和 270°方位(即水平方向左、

Tube Body And Law Orchid Group To

of the cylinder, longitudinal seam direction to the 90 ° and 270 ° azimuth (horizontal left and right sides direction), divided equally flange holes, quartered。 4.用铅垂线或水平尺将有一端法兰的筒体调节好,要求 0°~180°跨中线与铅垂线重合。Adjust the one end flange of the cylinder by the plumb line or level ruler, require the 0 ° to 1 80 ° crossing center line and plumb line to coincid e with each other. 即管箱法兰铅垂线与跨中等分线要求与上法兰相同条件 (即螺栓孔跨中) Assemble the other end of the flange, thus 。 5.组对另一端法兰, the tube box flange plumb line shares the same condition with the middle-point line (thus the bolt hole is at the middle). 6.装配间隙 0~1.5mm,错边量 0~2mm。The assembly gap is 0~ 1.5mm, the staggr mount is 0 ~ 2mm. 用卷尺在 0°、 测得壳体长, 长度偏差 2mm。 筒体总长控制在 ( ) ±3mm。 Detecte 7.检测两端法兰面水平度, 90°、 180°、 270°四个方位, the level degrees of both ends of the flange, use the tape measure at 0 ° 90 ° 180 ° 270 ° , , , four card inal position, measure 。 the shell length, the deviation is 2mm. The barrel length is contled at () ± 3mm 8.检测、 焊接完毕后, 对筒体环缝内打磨平, 送探伤检测, 要求 RT≥ ) Ⅲ级合格。 After detection and welding, polished flat within ( %, the seam of the cylinder ring, sending the flaw to detect, requst the RT ≥ () class, III qualified.

编制/日期:

校对/日期:

审核/日期:

-2-

浮头式换热器制造工艺作业指导书

Floating head heat exchanger manufacturing operating instructions

接管与法兰 Nozzle and

将坡口加工好的接口与相对应法兰进行组装,要求:间隙 3~4mm,错边在 1.5mm 以下,氩弧焊打底,全熔透结构。焊接完成后送无损检测,检 验标准 RT≥( )%,Ⅲ级合格。Assemble the groove machined nozzle with the corresponding flange, requirements: the gap

the flange

is 3 ~ 4mm, the staggered side is less than 1.5mm, argon arc bottoming, full penetration structure. After welding,having a non-destructive testing, the inspection standards is RT ≥ () class, III qualified. 筋板、 立板进行组装前的检查。 accordance with drawings, inspect the supports backplane, ribs, riser before In 支 座 点 焊 1.按图对支座的底板、 assembling. Supports 2.组装各部件,点固,加支撑件等,焊接。Assemble every component, solid point, support pieces, and welding. welding
1.按先前标出的 0°、 90°、 180°、 270°方位点,延长在壳体上。 Base on the previously marked 0 ° 90 ° 180 ° 270 compass points° , , , ,

extending to the hcase.
2.画出接管、支座,预开孔,安装位置,即坐标点。Draw the nozzle, supports, pre-openings, the installation location, that is, the 接管支座与 壳 体 组 装 Nozzle

coordinates of points
开孔, 然后打上坡口, 角度为外坡口 30°After Inspection, opening, then grooving,the angle of the outer groove is30 ° 3.检验合格后, 4.组对接管与壳体,组装前,接管必须将补强圈带上固定好,一起装配。Connect nozzle to shell, before assembling,the nozzle must

supports
and shell

fix the reinforcement ring,along with the equipment. 5.接管与壳体组对间隙为 2~3mm,且间隙均匀。The gap of the nozzle and shell is 2 ~ 3mm, and the gap is uniform After welding, to nozzle requires to clear the root of the

assembling
6.焊接完毕后,内接管须清根封底,焊缝打磨与母材齐,并倒 2×45°圆角。

back cover, weld and polise to ensure the base metal level, and the fillet is 2 × 45 ° .

编制/日期:

校对/日期:

审核/日期:

-3-

浮头式换热器制造工艺作业指导书

Floating head heat exchanger manufacturing operating instructions

1.封头:材质确认,标记移植,切割,外协模压,回厂检验,材质为( ) ,δ( ) Head: Material confirmation , mark and transplante, 。

管箱 Tube box

cutting, outsourcing molding, back to the factory inspection, the material is (), δ (). 2.短节: 材质确认 a.按排版图尺寸划线下料坡口加工。 见具体工艺文件) Short section: material confirmation a. Drawing, crossed ( material and groove processing by the size of the layout chart. (See the specific process documents). b.卷板,纵缝焊接,校圆,纵缝 RT≥( )%,Ⅲ级合格,车加工削薄。 b. coil, longitudinal seam welding , regulate round, longitudinal seam RT ≥ (), III class qualified ,vehicle processing thinning. 3.管箱法兰与短节组装: a.管箱法兰与短节组焊, 封头与短节组焊。 Flange and short section of the tube box assembly: a. tube box flange and a short section welding,the head and a short section welding。 b.对环缝进行射线检测。Ring sewn-ray detection. c.与壳体联接,整体划线,开孔,接管组装,焊接,确保其整体一致性。Connection with the shell, the overall drawing, openings, nozzle assembly, welding, ensure that its overall consistency.
d.卸下管箱,对接管法兰清根封底,划出隔板安装线,再按封头实样放样切割,装配隔板和焊接,装配要求:每层隔板端口尺寸必须与固 定端管板 ) ( 槽一致吻合。 Remove the tube box, clear the root of the nozzle of the flange, draw the bulkhead install line, and (d)

then cutting base on the real shape of the head, assembling the bulkhead and welding, assembly requirements:each partition port size must be consistent with the fixed end of the tube plate () notch.
e.做好热处理前支撑,防止热处理使隔板变形。

Do good support before heat treatment to prevent heat treatment so that bulkhead deformation f.热处理完毕冷却后,再加工密封面,保证法兰密封面与隔板端平面一致。After the heat treatment and cooling, reprocessing the sealing surface to ensure the flange sealing surface and the baffle-side plane consistent.

编制/日期:

校对/日期:

审核/日期:

-4-

浮头式换热器制造工艺作业指导书

Floating head heat exchanger manufacturing operating instructions

1.封头:材质确认 划线,标记移植,切割,外协模压,回厂检验,贴合格标签。Head: The material confirmation, mark and transplante, 外 头 盖

the outside bonnet

cutting, outsourcing molded, back to the factory inspection, paste qualified label. 2.短节:材质确认 按图尺寸划线,切割,坡口精加工,卷板,焊接,校园。Short sections: materials confirmation drawing base on the size of the chart, cutting and finishing of the groove, plate bending, welding, regulate round. 3.法兰与封头,短节组焊:a.将合格封头和短节及对应法兰组焊,错边量控制在 0~2mm 之间。Flange and the head, a short section of welding: (a) welding the qualified head ,a short section and the corresponding flange, the stagger volume is controlled between 0 ~ 2mm. b.环缝焊接,无损检测。(b).The girth welding, nondestructive testing. c.划线开孔,安装管嘴和吊耳,焊接 (c). Drawing and opening, install the nozzle and lug ,welding. d.与壳体、管箱、浮头盖,一并整体热处理。(d).The shell, tube box, floating cover, together with the overall heat treatment.
1.拱盖:材质确认 划线下料,标记移植、切割,外协模压、回厂检验。Ledge: material confirmation

Drawing and cutting, mark

transplantation, cutting, outsourcing molding, back to the factory inspection. 2.浮头法兰: 在材料检验员指定下领取贴有合格标签的法兰。 Floating head flange: receive designated qualified label of the flange 浮 头 盖 under the guidiance of the materials inspector . Floating 3.将拱盖与浮头法兰组装,装配尺寸如图。Assemble ledge and floating head flange, the assembly size shown in Figure。 4.焊接完毕后,再按拱盖的实形放样、隔板、切割、组装、焊接,确保隔板装配尺寸与浮动管板槽尺寸一致。After welding, the then loft bonnet base on the real shape, bulkhead,cutting, assembling, welding, ensure size of the bulkhead, assembly size and floating tube notch groove consistent. 5.与前壳体、外头盖及管箱一并进炉热处理。Having a heat treatment furnace to the front shell, the outside bonnet and the tube box . 1.材质确认:φ( )×( ) 规格( ) Material confirmation: φ( )×( ) Specification(). 。 换热管 2.单管试压,试验压力为设计压力的 2 倍,即( )MPa。Single-tube testing pressure,the pressure is 2 times the design 管束 tube pressure,that is () MPa. bundle

编制/日期:

校对/日期:

审核/日期:

-5-

浮头式换热器制造工艺作业指导书

Floating head heat exchanger manufacturing operating instructions

本锻件应按 JB4726 制造与验收,进行 PT 检测,依图数控放样、钻孔、隔板槽铣加工、倒坡口、拉丝孔攻丝。The forgings shall

be JB4726 manufacture and acceptance ,PT detection, according to Figure NC loft, drilling, the bulkhead.slot milling, chamfer the groove, wire drawing hole tapping. 1.材质确认,Q235B,δ16,数控放样切割,去渣,整形,打垛点固焊。Material confirmation,Q235, δ16, CNC cutting loft, remove the residue, shaping, playing stack point of solid welding. 折流板 2.数控划线,钻孔,折流板车园,做标记顺序号,单块剪切去毛刺。NC drawing, drilling, baffle to car round, mark the order number, a single block of shear deburring. 3.顺序号移植,管孔倒角,折流板打磨,整形。Sequence number transplantation, pore chamfer, baffle polished, plastic
管板 其它 辅件 加工 定距管机加工, 拉杆端点过丝, 滑道旁路挡板剪切下料、 整形。 Distance tube machining, rod endpoint wire, slide the bypass

damper shear cutting, shaping.
1.立架:先将固定管板直于工装平台架上,依次按图安装拉杆、距管、折流板,锁紧拉杆螺姆。Stands: first fixed tube plate

管束

管束 组装

管束 试压

straight to the tooling platform rack, followed by the plan to install the rod ,the distance tube, baffle, locking lever screw farm 2.处理管板孔和管板面上的油污、锈蚀等。Dealing with the tube sheet holes and the tube sheet surface oil, corrosion, etc. 3.穿管: 穿管完毕后再上浮动管板, 定尺定位, 点焊, 再回管。 Tube cross: crossing the tube ,then installing the floating tube sheet, length positioning, spot welding and then back to the tube. 4.管头焊、切管、打磨、浮动端管头焊,支耳调试,安装焊接,管头两端热处理。Tube head welding, tube cutting, polishing, floating side tube head welding, lugs debugging, install the welding, the tube head at both ends of heat treatment 5.胀管(见胀管工艺卡) ,胀管器按编号到仓库领用,规格为φ( )×( )—( ) Expander (see the expanding technology 。 card), the expander by number to the warehouse recipients, specifications are φ( )×( )—( ). 6.安装滑道并焊接。Installation of slide and welding 管头试压,试验压力( )MPa(见试压工艺)水压试验时下列情况为合格:无渗漏,无可见变形,过程中无异常响声。Tube head pressure test, the test pressure is () MPa (see Pressure Test) .hydrostatic test, the following conditions are eligible: no leakage, no visible distortion, no abnormal noise in the process.

编制/日期:

校对/日期:

审核/日期:

-6-

浮头式换热器制造工艺作业指导书

Floating head heat exchanger manufacturing operating instructions

1.将管束试压合格后,装入壳体中 After passing the pressure test,put the bundle into the shell. 2.安装两端管箱,浮头盖,装配时注意垫片的保护,均匀将几件螺栓紧固。安装管箱,浮头盖时,一定做好隔板槽和隔板衔接口标记,稳合 统一。Install both ends of tube box, floating bonnet ,pay attention to the protection of the gasket assembly, bolt a few

pieces evenly. When installing the pipe box, floating head cover, be sure to do the partition groove and clapboard convergence mouth mark, stable co-unified. 3.螺栓拧紧时,要分步骤,先预紧等分四颗,即 0°、90°、180°、270°,再逐步对称紧固。用力要均匀,最后对螺栓进行全面紧固。When overall pressure tightening the bolts, step by step, decile four first , namely, 0 ° 90 ° 180 ° 270 ° and then grad ually tighten the , , , , test symmetry. Forced evenly, at last full tightening the bolts.
整 体 试 压 ( 4.将管箱上( )孔,即下端接管用盲板封住,紧螺栓, )注水,用行车配合作业,上下来回起落,将管程中空气排净为止,状态为不显 现汽泡静止面, 再封住 ( ) 紧固螺栓。 口, Tube box () hole, seal the bottom nozzle by the blind plate,bolt, () inject, operate with

a driving car, up and down, until draining the process air of the tube , the state does not show bubble stationary surface, and then sealed () and tighten the bolts. 5.按试压工艺卡,分步骤循序淅升。According to the pressure test card, step-by-step sequential Hsi-l. 6.检验易池漏区、面和焊道,无泄漏,无异常响动为合格。Test the leak area, surface and weld, no leaks and no unusual ring for qualified. 7.组装外头盖,同上紧固螺母,封堵壳程( )口和外头盖下方管嘴。Assemble the bonnet, ditto fastening the nut and sealing the shell ()outlet and the nozzle below the outside bonnet. 8.( )和( )注水,同上方法排净空气,封住( )和( )口,紧固螺栓。()and () injection, ditto drain the air, seal () and() port and tighten the bolts. 9.稳步升压至试验区域线,检查,无漏点和异样响声为合格。Steady boost to the test area line, check no leak point and strange sound for qualified. 10.排净体内积水,用压缩空气吹干。Drain the body of water, dry with compressed air.

编制/日期:

校对/日期:

审核/日期:

-7-

浮头式换热器制造工艺作业指导书

Floating head heat exchanger manufacturing operating instructions

外观处理, 喷砂时对螺栓要做好保护措施, (见工艺卡) 油漆 包装。 11.喷砂, Sandblasting, processing the appearance,when blasting

the bolts ,taking protective measures, painting (see process card) packaging.

编制/日期:

校对/日期:

审核/日期:

-8-


相关文章:
换热器制造工艺规程
换热器制造工艺规程_机械/仪表_工程科技_专业资料。详细描述管壳式换热器的制造工艺流程及其要求,是保证换热器质量的重要作业文件 管壳式换热器制造工艺规程 1、主题...
列管式换热器工艺流程简介
列管式换热器工艺流程简介_能源/化工_工程科技_专业资料。列管式换热器工艺流程简介换热器是进行热交换操作的通用工艺设备,广泛应用于化工、石油、石油化工、动力、冶...
管式换热器制造流程框图及简要说明
换热器制造工艺指导流程 8页 2下载券 换热器所有构件制造工艺... 20页 4下载券...换热器质量控制点 4页 免费管​式​换​热​器​制​造​流​程...
列管式换热器工艺流程图
⑧压降小于 设计压力 裕度系数校验 考虑夏冬季 的温度差异, 改变冷流体 进口温度 ⑨ 裕度合适 ⑩ 确定换热器基本尺寸 计算换热器其余零件 工艺流程图 水 煤油 水...
换热器产品技术部设计、工艺流程规范
各种换热器设计详细说明... 85页 1下载券 换热器制造工艺指导流程 8页 2下载券...换热产品技术部设计、工艺流程规范为了适应公司的发展,规范目前的工作程序,提高...
换热器作业指导书
换热器作业指导书_机械/仪表_工程科技_专业资料。一、换热器检修流程 二、换热器...堵管数一般不得超过管束管子总数的 10%(根据本厂工艺和生产情 况可适当增减)...
换热器作业指导书
4.项目组织结构及质量保障体系 4.1 施工组织网络 车间总负责人 生产安全负责人 ...施工程序、方法及技术措施换热器检修工艺换热器检修主要作业是进行设备清洗,改善...
浅谈换热器制造过程中的控制要点
浅谈换热器制造过程中的控制要点 摘要:换热器是目前国内石油化工行业中最常用的...在化工生产中随着热量释放与交换的频繁发生,加热能使化学反应达到 最佳工艺条件,...
板式换热器的制造工艺
全焊接板式换热器制造工艺和简介 摘要:简要介绍了全焊接板式换热器的芯体和外壳的制造工艺以及在制造过程中所采用的焊接技术。通 过介绍可知,全焊接板式换热器是一...
换热器制造工艺卡
管壳式换热器制造工艺 32页 2财富值如要投诉违规内容,请到百度文库投诉中心;如...按本厂压力容器用材料进厂检验程序进行入厂检验,须有材质证明 书,材料标记应...
更多相关标签:
换热器制造工艺 | 板式换热器工艺流程图 | 换热器工艺流程图 | 换热器生产工艺流程图 | 换热器工艺流程 | 换热器制造流程 | 晶圆制造工艺流程 | 模具制造工艺流程 |